Turnkey Property Renovation on the Costa Blanca: What to Expect


A turnkey renovation means one company manages the whole project, from the first survey and the permits to every trade on site and the final handover, so you receive a finished home rather than a list of contractors to coordinate. On the Costa Blanca it suits owners of second homes, buyers of older apartments and villas, and anyone living abroad who cannot supervise builders day to day. This guide explains what is normally included, what sits outside the scope, which permits apply, how costs are built up and how to protect yourself in writing.
Key Takeaways
A genuine turnkey service covers design, permits, all trades, supervision and snagging under one contract, one schedule and one point of contact.
Cosmetic and non-structural work generally needs a minor works licence; extensions, structural changes and pools need a major works licence with an architect’s project, and the town hall can take months to resolve it.
Regional cost data for 2026 puts light renovation at EUR 350–650/m² and full renovation at EUR 700–1,100/m², but only an itemised, closed quote gives you your real figure.
Compare at least three like-for-like quotes and agree the payment calendar, delay penalty and guarantee in the contract before work starts.
If you live abroad, insist on written approval of every change and regular photo and video reports.
Table of Contents
What a turnkey renovation actually includes
The phrase is used loosely, so define it in the contract. In our experience a properly scoped turnkey project has five layers:
Assessment and scope. A site visit, a check of the property’s condition (damp, electrics, plumbing, roof, façade) and a written specification.
Design and layout. Interior design, space planning and material selection, including kitchens, bathrooms, flooring and joinery.
Permits and paperwork. Identifying the licence the works require and preparing or coordinating the documentation with the town hall.
Execution of all trades. Demolition, plastering, plumbing, electrical work, carpentry, tiling, painting, air conditioning and finishing, sequenced by one project manager.
Handover. A snagging inspection, correction of defects and delivery of the certificates and documentation.
At URU Reformas this maps onto the services we run in-house in Torrevieja and the Vega Baja: full renovation, extensions, façade, kitchen, bathroom and roof waterproofing work, plumbing, electrical installations, carpentry, painting and interior design.
What usually sits outside the scope
Some items are commonly priced separately, and a quote should say so plainly rather than leave them to assumption:
Architect’s fees for a major works project, and the municipal licence fee and ICIO construction tax.
Furniture, soft furnishings and appliances, unless the specification lists them.
Community of owners’ approvals for apartment façades, terraces or shared pipework.
Landscaping and garden work beyond the pool and terrace.
Hidden defects found once walls are opened, which should be handled through a written change order.
Ask for a line stating what is excluded. A closed quote is one with no unforeseen costs, and that only works if the exclusions are listed.
The process from survey to handover
The sequence below is the one we recommend owners expect, whichever company they choose.
Initial conversation and site visit. The contractor measures, photographs and notes problems such as damp or ageing installations.
Written scope and specification. Materials, brands, finishes and quantities are fixed so that quotes can be compared.
Phased, itemised quote. Each trade is priced separately with unit calculations.
Permit application. A minor works licence for non-structural work, or a major works licence with an architect’s project for structural work.
Contract signature. Start and finish dates, payment calendar, penalties and guarantee are written in.
Execution with supervision. One manager coordinates trades and reports progress.
Snagging and handover. A defect list is drawn up and corrected before the final payment.
For a deeper look at timing, see our guide on how long a complete home renovation takes in Spain.
Pro Tip: Do not let demolition begin until the licence situation is clear. Starting work before the right permit is in place is the most avoidable cause of stoppages.
Permits: minor works versus major works
The permit type depends on how far the work changes the building.
A licencia de obra menor covers non-structural work such as kitchen and bathroom renovations, replacing floors and tiles, swapping windows and doors in the same opening, and electrical and plumbing updates. According to a Costa Blanca licensing guide, clear cases usually take one to four weeks, with an administrative fee of around €100–€300 plus ICIO.
A licencia de obra mayor is needed when work significantly changes a property’s surface, volume, structure or exterior appearance. The same guide lists buried or permanent swimming pools, extensions, structural pergolas, work on load-bearing walls and garage conversions into living space. A licensed architect must draw up and sign the project, and the town hall can take three to six months to issue its resolution. Another overview of renovation regulations in Spain draws the same line between the two licence types.

For a full reform of a home, the practical consequence is a longer pre-construction phase. Plan for it before you set a move-in or letting date. Our article on which renovation permits are required in Alicante goes into the detail, and the exact requirements always rest with your own town hall, so confirm them there for your property.
How turnkey renovation costs are built up
A per-square-metre figure is a starting point, never a quote. Regional data for the Costa Blanca in the first quarter of 2026 from Zaminor gives these indicative ranges:
Work | Indicative range (Q1 2026) |
Light renovation (kitchen, bathroom, painting, floors) | EUR 350–650/m² |
Full renovation (structure, layout, installations) | EUR 700–1,500/m² |
Complete kitchen renewal | EUR 5,000–15,000 |
Complete bathroom | EUR 3,000–10,000 |
Complete electrical installation | EUR 3,000–8,000 |
Air conditioning split unit | EUR 800–1,500 per unit |
Swimming pool (8 x 4 m) | EUR 15,000–30,000 |
These are market ranges from a third party, not URU Reformas prices. We do not publish fixed prices because every property differs; our quotes are free, detailed and phased, and work is billed by contract according to scope. See our breakdown of what a Costa Blanca renovation costs in 2026.
What moves a quote up or down
Condition of installations. Old wiring, galvanised pipes and hidden leaks widen the scope once opened up.
Damp and waterproofing. Coastal humidity and salt affect terraces, roofs and façades, and the correct impermeabilisation system adds cost but protects everything built on top.
Layout changes. Moving a kitchen, removing walls or relocating bathrooms means new plumbing runs and possibly a major works licence.
Specification. Tile format, kitchen cabinetry, sanitary ware and glazing quality swing totals more than labour does.
Access and logistics. Upper-floor apartments without a lift, narrow streets and community working-hour rules affect time on site.
Timing. Rushing a finish date before a rental season can limit sequencing and raise cost.
How to compare quotes properly
The consumer organisation OCU advises obtaining at least three comparable quotes that state the type and duration of the guarantee. It adds that they should be complete and closed, itemised by trade, and based on unit calculations (per m², linear metre, unit) with qualities and models specified.
In practice that means building a comparison sheet:
Check | What a good quote shows |
Scope | Each trade listed, with exclusions stated |
Materials | Brands, models and qualities named |
Measurements | Unit prices per m², metre or item |
Permits | Who applies, and who pays fees |
Programme | Start date, finish date, phases |
Guarantee | Length and what it covers |
Payments | Calendar tied to progress |
Also check the company itself. Zaminor suggests verifying registration in the Registro Mercantil, proof of liability insurance, and three to five recent references. For a local angle, our guide to choosing a renovation company in Torrevieja shows how to build a shortlist of three to five firms.
What to agree in writing before work begins

The contract is the real project plan. According to OCU, it should specify start and completion dates, a delay penalty, a payment calendar, and the agreed guarantee period and conditions. On payments, OCU recommends no more than 20–30% at the start, successive payments as works progress, and a final payment of around 30% on satisfactory completion. Zaminor proposes a slightly different split and a retention of at least 10% until handover is fully satisfactory. Either way, the principle is the same: money follows verified progress.
Agree these points in writing:
Materials: named products or approved equivalents.
Changes: every variation priced and approved in writing before it is carried out.
Invoices: matched to completed work before payment.
Defects: how snagging is carried out and the deadline to correct items.
Handover: the certificates and documentation delivered, such as electrical paperwork where applicable.
Insurance and compliance: proof the contractor holds liability cover and works to current regulations.
Pro Tip: Photograph each phase before it is covered up: pipework in walls, waterproofing layers on terraces, cabling behind plaster. Those images are valuable evidence later.
Managing a renovation from abroad
Many of our clients are British, Irish, Dutch, German, Nordic and Eastern European owners who spend only part of the year in Spain. A remote project works when four things are in place:
One point of contact who speaks your language and answers within an agreed time.
Scheduled reporting: weekly photo and video updates tied to the programme, not ad hoc messages.
Written approvals: decisions on tiles, layouts or extra work confirmed by email, so nothing is assumed.
Authority to act: if paperwork requires your signature or a representative, arrange this early. We cover this in renovating a Spanish property from abroad and in what foreign homeowners should know before renovating in Spain.
A site visit at the start, one at the midpoint and one for the snagging walk-through, in person or by video, gives you control without having to live on site.
Our perspective
Over the years we have seen that most renovation problems on this coast begin before the first tile is laid: an unclear scope, a permit assumed rather than confirmed, or an installation hidden behind a wall that nobody inspected. That is why we work from a diagnosis first. We survey the property, identify damp, ageing electrics and plumbing, and then present a free, detailed, phased quote so that each stage has its own price and programme. Because plumbing, electrical work, carpentry, painting, plastering, air conditioning and interior design are all part of what we do, one team sequences the trades and the weakest link does not hold up the others. Our approach is built on guaranteed pricing, deadlines and quality, with insurance and regulatory compliance handled from start to finish. For owners abroad, that means clear communication, photographic updates and a single contract rather than a string of subcontractors to chase. We believe a renovation done once, with the right waterproofing, the right installations and the right paperwork, is the one that adds comfort and value for years. URU Reformas
Start your renovation with a single contract
If you own an apartment, villa or holiday home in Torrevieja, Orihuela Costa, Ciudad Quesada or elsewhere in the Vega Baja, we can take the project from survey to handover. Our renovation services cover complete and partial renovations, bathrooms, kitchens, façades, extensions and roof waterproofing, with new builds and swimming pools handled by the same company.

Request a free consultation and a detailed quote through our website, and tell us whether you are renovating to live in, to rent or to sell.
Avoiding the usual problems
A few habits protect almost any project. Diagnose before you design, so damp and installation problems are in the budget from day one. Keep the specification stable once the contract is signed. Confirm permits before demolition. And read our guides on how to avoid common renovation problems on the Costa Blanca and what to expect when renovating a villa. If you are still buying, four checks before buying a property to renovate can save you from an unsuitable purchase.
FAQ
How long does a turnkey renovation take?
It depends on scope and permits. A partial, non-structural reform can start within weeks of a minor works licence, while a full reform needing a major works licence can add several months before work begins. Your contractor should give you a written programme with start and finish dates.
Is a turnkey renovation more expensive than hiring trades separately?
You pay for coordination, but you also gain one contract, one guarantee and one schedule. Comparing three itemised quotes, as OCU recommends, is the best way to see what each approach includes for your property.
Do I need a licence to renovate my kitchen or bathroom?
Usually a minor works licence, because these are non-structural works, according to the licensing guide above. Your town hall confirms the exact requirement, and we can coordinate it as part of the project.
Can I run the project while living abroad?
Yes, with a single point of contact, scheduled photo and video reports, and written approval of every change. Arrange early any paperwork that needs your signature or a representative.
How much should I pay upfront?
OCU suggests no more than 20–30% at the start, with later payments tied to progress and around 30% on satisfactory completion. Put the calendar in the contract.